Exchange Square Office Reinstatement – 1,300 sq ft Returned in 4 Weeks

Agrey meets every HKL reinstatement rule

· Case Studies,Office Reinstatement
Looking up at the twin glass-clad towers of Exchange Square in Central, Hong Kong, with the cursive ‘Exchange Square’ entrance signage visible at street level

Exchange Square Towers 1 & 2, the iconic mixed-use complex in Central, Hong Kong, where Agrey Reinstatement returned a 1,300 sq ft fitted office to bare shell in just 4 weeks—fully compliant with Hongkong Land’s reinstatement obligations and coordinated nominated-contractor works.

Composite showing lobby directory for 34/F One Exchange Square and carpet-protected core corridor with hoarding in place

↑ Tenant directory and corridor protection installed to meet Hongkong Land’s housekeeping rules.

Side-by-side comparison of Suite 3407 before (partitioned, timber floor, feature wall) and after reinstatement as a bare-shell concrete slab.

↑ Before & after: partitions, flooring and feature wall stripped out, returning the suite to landlord bare-shell standard.

Three-frame collage of HVAC duct removal and ceiling services demolition during Week 1 strip-out at Exchange Square

↑ Week-1 demolition: ducts, conduits and ceiling services removed during night-shift noisy-work window.

Four-image collage of completed Suite 3407: open concrete slab, repainted walls, reinstated WG acoustic ceiling and close-up of panel/air-grille junction

Hand-back complete: 1,300 sq ft suite returned pristine, ceiling grid and penetrations reinstated to HKL spec.

Street-level view of the twin cylindrical glass towers of Exchange Square in Central Hong Kong under a bright sky

Exchange Square’s iconic twin towers served as the backdrop for Agrey’s 1,300 sq ft office reinstatement, where we delivered a clean shell back to Hongkong Land in just four weeks—fully coordinating builder services and nominated contractors per the landlord’s requirements